5.2 Receipt Nominations and Allocation Methodology (continued)
11:45 a.m. Receipt of nomination by Transporter
(including from TTTSPs).
12:00 p.m. Transporter sends Quick Response.
3:30 p.m. Receipt of completed confirmations
by Transporter from upstream and
downstream connected parties.
4:30 p.m. Receipt of scheduled quantities by
Shipper and Operator.
(2) The Evening Nomination Cycle on the Day prior to
Gas flow shall be as follows:
6:00 p.m. Nomination leaves control of the
nominating party.
6:15 p.m. Receipt of nomination by Transporter
(including from TTTSPs).
6:30 p.m. Transporter sends Quick Response.
9:00 p.m. Receipt of completed confirmations
by Transporter from upstream and
downstream connected parties.
10:00 p.m. Transporter provides (which, for
purposes of this Section 5.2(a) and
Section 5.5(a) below, shall mean,
for electronic data interchange
transmittals pursuant to NASEB
Standards 1.4.X, receipt at the
designated site, and for other forms
of transmittal, sending and posting)
scheduled quantities to Shipper and
Operator, including notice to bumped