Centerpoint Energy Gas Transmission Company
Sixth Revised Volume No. 1
Contents / Previous / Next / Main Tariff Index
Effective Date: 01/01/2010, Docket: RP10-206-000, Status: Effective
Eighth Revised Sheet No. 315 Eighth Revised Sheet No. 315
Superseding: Seventh Revised Sheet No. 315
GENERAL TERMS AND CONDITIONS
(continued)
1. DEFINITIONS AND INTERPRETIVE MATTERS (continued)
Interim Service. See Section 10.4(c).
IT Cash Balancing Revenue Credit. See Section 5.7.
IT Credit Account. See Section 5.7.
IT Crediting Revenues. See Section 23.2(b)(iv).
IT Revenue Credit. See Section 23.5.
Line CP shall mean CEGT's 42-inch diameter pipeline extending from
the Carthage hub area in east Texas to CEGT's Perryville Hub in
northeast Louisiana.
Line CP Fuel Use shall mean Gas consumed by compressors and other
gas handling equipment and company use gas on CEGT's Line CP.
Line CP Fuel Use and LUFG shall mean Line CP Fuel Use and Line CP
LUFG.
Line CP LUFG shall mean Gas lost or otherwise unaccounted for on
CEGT's Line CP.
Line CP Pooling Area shall mean an area containing Line CP and all
Receipt Points into Line CP, the Perryville Hub Header and all
lateral lines off Line CP.
Line J Backhaul shall mean a transaction involving volumes
received at receipt points on Line J between the Searcy and White
River interconnects and delivered by displacement backhaul to
Texas Gas at the Searcy Interconnection.
Line J Backhaul Fuel Use shall mean Gas consumed by compressors,
other gas handling equipment and company use gas at the Searcy
Compressor Station.
Line J Backhaul LUFG shall mean Gas lost or otherwise unaccounted
for associated with volumes received into Line J between the
Searcy Interconnection and the White River Interconnection and the
volumes delivered to Texas Gas at the Searcy Interconnection.