Centerpoint Energy Gas Transmission Company
Sixth Revised Volume No. 1
Contents / Previous / Next / Main Tariff Index
Effective Date: 05/01/2010, Docket: RP10-567-000, Status: Effective
First Revised Sheet No. 52 First Revised Sheet No. 52
Superseding: Original Sheet No. 52
RATE SCHEDULE FT
FIRM TRANSPORTATION SERVICE
(continued)
5. MONTHLY BILL (continued)
(a) The product of the Reservation Charge, if applicable,
and each Dth of Contract Demand;
(b) The product of the Commodity Rate or the Small
Customer Commodity Rate, as applicable, and the total
Dth of Gas delivered during the Service Month up to
applicable Contract Limitations;
(c) The product of the Overrun Rate or the Small Customer
Overrun Rate, as applicable, and the total Dth of
Overrun Gas, whether authorized or unauthorized,
received, transported and/or delivered during the
Service Month.
5.2 Adjustments.
(a) Failure to Deliver Contract Demand: If during one or
more Days in the Service Month Transporter is unable
to deliver to a Shipper which is paying the maximum
rate, including a Reservation Charge, Gas scheduled
and received by Transporter for the account of
Shipper, up to the Contract Demand, consistent with
other Contract Limitations, established for the
Service Month, then, for Shippers paying the maximum
rate, the total applicable Reservation Charge shall be
reduced by subtracting the product of the quantity of
such Gas in Dth which Transporter did not deliver and
the applicable currently effective Reservation Charge
Adjustment Rate. For Shippers paying less than the
maximum rate, the amount of the adjustment, if any,
shall be