Keyspan LNG, LP (Alng)
Third Revised Volume No. 1
Contents / Previous / Next / Main Tariff Index
Effective Date: 01/27/2003, Docket: RP03-241-000, Status: Effective
Original Sheet No. 82 Original Sheet No. 82 : Effective
Joseph A. Vaszily, Vice President
GENERAL TERMS AND CONDITIONS
(continued)
19. SCHEDULING OF SERVICE (continued)
19.2 LNG Receipts and Deliveries by Truck.
(a) LNG Receipts by KLNG:
(1) Firm. Requests for LNG receipts by truck for firm
Customers shall be scheduled in advance of the
allocation of any truck handling capacity to
interruptible Customers. Subject only to Sections 17
(Force Majeure) and, 18 (Curtailment) of these General
Terms and Conditions, KLNG shall schedule each firm
Customer's truck nominations up to its Maximum Number
of Trucks. In the event that the sum of all timely
nominations by firm Customers for truck handling exceed
KLNG's truck handling capacity, the available capacity
shall be allocated among Customers submitting
nominations pro rata on the basis of their firm
Contract Storage Quantity, rounded to the nearest
truckload.
(2) Interruptible. In the event that capacity remains
available after the scheduling of all requests for LNG
receipts by truck for firm Customers, requests for LNG
receipts by truck by interruptible Customers shall be
scheduled, rounded to the nearest truckload, (1) among
Customers paying the maximum applicable rate on a
first-come, first-served basis based upon the priority
assigned to Customer's request, then (2) among
Customers paying a discounted rate on the basis of the
rate being paid, with the Customer paying the highest
rate having the highest priority.
(b) LNG Deliveries by KLNG:
(1) Firm. Requests for LNG deliveries into trucks for firm
Customers shall be scheduled in advance of the
allocation of any truck handling capacity to requests
for LNG deliveries into trucks for interruptible
Customers. Subject only to Sections 17 (Force
Majeure), and 18 (Curtailment) of these General Terms
and Conditions, KLNG shall schedule each firm
Customer's truck nominations up to its Maximum Number
of Trucks. In the event that the sum of all timely
nominations by firm Customers for truck handling exceed
KLNG's truck handling capacity, the available capacity