Algonquin Gas Transmission, LLC

Fifth Revised Volume No. 1

 Contents / Previous / Next / Main Tariff Index

 

 

Effective Date: 11/30/2009, Docket: RP10-77-000, Status: Effective

Second Revised Sheet No. 584 Second Revised Sheet No. 584

Superseding: First Revised Sheet No. 584

 

GENERAL TERMS AND CONDITIONS

(continued)

 

28. DETERMINATION OF DELIVERIES (continued)

 

 

(i) Rate Schedule AFT-E. In the event Customer has scheduled deliveries of gas under

Rate Schedule AFT-E on any Day, the total quantity delivered by Algonquin to

Customer on any Day, less the quantities determined pursuant to (a) through (h)

above but not in excess of the scheduled quantities if Customer has scheduled

quantities to be delivered under the rate schedule listed in (j). In the event

that Customer has not scheduled quantities to be delivered under (j), the total

quantity delivered by Algonquin to Customer on any Day, less the quantities

determined pursuant to (a) through (h) above shall constitute the deliveries on

such Day under Rate Schedule AFT-E.

 

(j) Rate Schedule AFT-ES. In the event Customer has scheduled deliveries of gas

under Rate Schedule AFT-ES on any Day, the total quantity delivered by Algonquin

to Customer on any Day, less the quantities determined pursuant to (a) through

(i) above shall constitute the deliveries on such Day under Rate Schedule AFT-ES.

 

28.4 Allocation of Deliveries Among Service Agreements. Whenever Customer is receiving

deliveries of gas at a Point of Delivery under more than one Service Agreement under a

particular rate schedule, and unless Customer specifies a priority for deliveries under

such Service Agreements after or during confirmation and before the effective time of

the gas flow, Customer's deliveries under that rate schedule, as determined in

accordance with Section 28.3, will be apportioned among such Service Agreements pro

rata according to scheduled quantities.

 

29. OPERATIONAL FLOW ORDERS

 

29.1 Purpose. In the event that Algonquin determines, in its reasonable discretion, that a

quantity of gas is required for use as Company Use Gas, Algonquin shall issue a flow

order pursuant to this section; provided, however, that this section may only be

invoked if Algonquin determines that such quantity of gas is not obtainable