Algonquin Gas Transmission, LLC
Fifth Revised Volume No. 1
Contents / Previous / Next / Main Tariff Index
Effective Date: 12/01/2009, Docket: RP10-146-000, Status: Effective
Fifth Revised Sheet No. 250 Fifth Revised Sheet No. 250
Superseding: Fourth Revised Sheet No. 250
RATE SCHEDULE AFT-1S
FIRM TRANSPORTATION SERVICE
as such lateral facilities are defined in Rate Schedule AFT-CL; provided, however,
that the interconnection between the Brayton Point Lateral and Algonquin's
mainline, the interconnection between the Manchester Street Lateral and
Algonquin's mainline, the interconnection between the Canal Lateral and
Algonquin's mainline, the interconnection between the Northeast Gateway Lateral
and the HubLine offshore system in Massachusetts Bay, Massachusetts, the
interconnection between the J-2 Facility and Algonquin's mainline, and the
interconnection between the Middletown Lateral and the Kleen Energy Lateral are
available as Secondary Points of Delivery under this Rate Schedule AFT-1S. Such
use of Secondary Points of Delivery is subject to and pursuant to Section 48.2 of
the General Terms and Conditions of this FERC Gas Tariff.
7. GENERAL TERMS AND CONDITIONS
The applicable General Terms and Conditions of this FERC Gas Tariff are hereby made a
part of this rate schedule.