Dominion South Pipeline Co., LP

Original Volume No. 1

 Contents / Previous / Next / Main Tariff Index

 

 

Effective Date: 12/16/2005, Docket: CP05- 77-001, Status: Effective

Original Sheet No. 1083 Original Sheet No. 1083 : Effective

 

 

GENERAL TERMS AND CONDITIONS

OFF-SYSTEM PIPELINE CAPACITY

 

 

29. OFF-SYSTEM PIPELINE CAPACITY

 

From time to time, Pipeline may enter into transportation and/or storage agreements with

other interstate or intrastate pipeline companies (off-system pipeline). In the event that

Pipeline acquires capacity on an off-system pipeline, Pipeline will only render service to

Customers on the acquired capacity pursuant to Pipeline's FERC Gas Tariff and subject to

Pipeline's approved and/or negotiated rates, as such tariff and rates may change from time to

time. For purposes of transactions entered into subject to this Section 29, the "Shipper

must have title" requirement is waived.