20. FERC ANNUAL CHARGE ADJUSTMENT

 

20.1 Purpose. For the purpose of funding of the Federal Energy Regulatory Commission's costs

incurred in any fiscal year, this Section establishes an annual charge adjustment

applicable to the Pipeline's transportation Rate Schedules as set forth on Sheet Nos. 50-69

of this FERC Gas Tariff.

 

20.2 Basis of the Annual Charge Adjustment. The Rate Schedules contained in this Tariff shall

include an increment for an Annual Charge Adjustment (ACA) for Federal Energy Regulatory

Commission costs. Such adjustment shall be the ACA unit charge, adjusted to the Pipeline's

pressure base and heating value, if required, which is specified by the Federal Energy

Regulatory Commission each year to recover its costs for its previous fiscal year. The ACA

shall be reflected on Sheet Nos. 50-69 of this Tariff. By electing the FERC ACA unit

charge method of recovery, Pipeline hereby acknowledges its intent not to recover any

annual charges recorded in FERC Account No. 928 in any general rate proceeding filed under

GT&C Section 4(e) of the Natural Gas Act.

 

20.3 Filing Procedure. The initial ACA or any subsequent changes in such charge shall be filed

by the Company at least 30 days prior to the proposed effective date, unless, for good

cause shown, a lesser notice period and different effective date is allowed by valid

Commission order. The proposed effective date of filings shall be October 1 of each

calendar year.