Dominion South Pipeline Co., LP

Original Volume No. 1

 Contents / Previous / Next / Main Tariff Index

 

 

Effective Date: 12/16/2005, Docket: CP05- 77-001, Status: Effective

Original Sheet No. 1049 Original Sheet No. 1049 : Effective

 

 

GENERAL TERMS AND CONDITIONS

CAPACITY RELEASE

 

15.6 Other Provisions.

 

A. Any Party may post offers to acquire capacity on Pipeline's Website for a period not

to exceed ten (10) Business Days.

 

B. Recall Provisions.

1. Releasing Customer's rights to recall capacity on a partial-day or full-day

basis shall be stated clearly in the posted notice of a release. The purchase

of Gas by Releasing Customer from Replacement Customer at the city gate shall

not be deemed an exercise of a recall provision.

 

2. Releasing Customer may recall capacity by complying with the provisions set

forth below. Releasing Customer may, to the extent permitted as a condition of

the capacity release, recall released capacity (scheduled or unscheduled) at the

Timely Nomination cycle, the Evening Nomination cycle, the Intra-Day 1

Nomination cycle, or the Intra-Day 2 Nomination cycle by providing notice to

Pipeline by the following times for each cycle: 8 a.m. CCT for the Timely

Nomination cycle; 3 p.m. or 5 p.m. CCT for the Evening Nomination cycle; 7 a.m.

CCT for the Intra-Day 1 Nomination cycle; and 2:30 p.m. CCT for the Intra-Day 2

Nomination cycle. For recall notification provided to the Pipeline prior to the

recall notification deadline and received between 7:00 a.m. and 5 p.m., Pipeline

will provide notification to all affected Replacement Customer(s) within one

hour of receipt of recall notification. For recall notification provided to the

Pipeline after 5 p.m. and prior to 7 a.m., the Pipeline will provide

notification to all affected Replacement Customer(s) no later than 8 a.m. after

receipt of such recall notification. Releasing Customer shall notify Pipeline

and the first Replacement Customer of its decision to recall capacity no later

than the timeline outlined below. Further, the daily contract entitlement for

partial-day recalls shall be allocated to the Releasing Customer and Replacement

Customer pro rata based on the effective time of the recall. This allocated

daily contract entitlement shall be used for purposes of nominations, billing,

and, if applicable, overrun calculations. Partial-day recalls shall not be

available for capacity released on a partial day. After exercise of a recall,

subject to agreement by the Releasing and Replacement Customers in accordance

with any provisions of the posted notice, Releasing Customer may reput the

recalled capacity to the original Replacement Customer, upon the same advance

notice to Pipeline that was required for the recall. When capacity is recalled,

it may not be reput for the same day. Replacement Customers that re-release

capacity shall also be responsible for notifying any later Replacement

Customers.

 

Early

Timely Evening Evening Intra-Day 1 Intra-Day 2

Recall Notification 8 a.m. CCT 3 p.m. CCT 5 p.m. CCT 7 a.m. CCT 2:30 p.m. CCT

To Pipeline and

First Replacement

Customer

 

Pipeline 9 a.m. CCT 4 p.m. CCT 6 p.m. CCT 8 a.m. CCT 3:30 p.m. CCT

Notification to

Replacement

Customer

 

Nomination 11:30 a.m. CCT 6 p.m. CCT 6 p.m. CCT 10 a.m. CCT 5 p.m. CCT

Possible Evening Cycle

 

Gas Flow 9 a.m. CCT 9 a.m. CCT 9 a.m. CCT 5 p.m. CCT 9 p.m. CCT

Next Gas Next Gas Next Gas Current Gas Current Gas

Day Day Day Day Day