GENERAL TERMS AND CONDITIONS
25. FORCE MAJEURE con't
25.3 Liabilities Not Relieved
Such causes or contingencies affecting performance by a party,
however, shall not relieve it of liability in the event of its
concurring negligence or in the event of its failure to use due
diligence to remedy the situation and remove the cause in an
adequate manner and with all reasonable dispatch, nor shall such
causes or contingencies affecting performance relieve a party from
its obligation to make payments of any amounts owed under
Shipper's applicable Service Agreement.
25.4 Scheduling of Routine Maintenance
Transporter shall have the right to curtail, interrupt, or
discontinue service in whole or in part on all or a portion of its
Pipeline Facilities from time to time to perform routine repair
and maintenance on Transporter's Pipeline Facilities as necessary
to maintain the operational capability of Transporter's Pipeline
Facilities or to comply with applicable regulatory requirements.
Transporter shall exercise due diligence to schedule routine
repair and maintenance so as to minimize disruptions of service to
Shippers and shall provide reasonable notice of the same to
Shipper.
25.5 Compliance with Directives of Governmental Agencies
Whenever, in order to comply with orders, directives or
regulations of duly constituted state, local or federal
authorities, including, but not limited to, the Department of
Transportation, the Federal Energy Regulatory Commission, and the
Environmental Protection Agency, Transporter must curtail
deliveries to or for the account of Shipper and is unable to
deliver to or for the account of Shipper the quantities of Natural