Nautilus Pipeline Company, LLC
Original Volume No. 1
Contents / Previous / Next / Main Tariff Index
Effective Date: 04/05/2010, Docket: RP10-475-000, Status: Effective
Third Revised Sheet No. 154B Third Revised Sheet No. 154B
Superseding: Sub Second Revised Sheet No. 154B
GENERAL TERMS AND CONDITIONS
14. DETERMINATION OF RECEIPTS AND DELIVERIES con't
(iii) the scheduled quantity of Authorized Overrun gas in
Dth for FT-1, FT-2, and FT-3; Transportation Service
Agreements;
(iv) the scheduled quantity of gas for PSH Transportation
Service Agreements;
(v) the scheduled quantity of gas for IT-1 Transportation
Service Agreements.
(c) At a location which is not covered by an OBA, a Confirming
Party should submit a Pre-determined Allocation (PDA) to
the allocating party at a level that is based on the
allocating party's business practice, but, in no event,
will such PDA be at a lower level (more detailed) than that
level of information exchanged between such parties during
their confirmation process.
(d) A Pre-determined Allocation (PDA) may not be used to
allocate gas to a nominatable transaction that was not
identified in the nomination or confirmation process, as
applicable, absent prior mutual agreement among the
Confirming Parties and the party being allocated to in such
transaction. In the event of a conflict between this
standard and Transporter's existing tariff or general terms
and conditions, the latter will prevail.
14.3 Prior Period Adjustments
Any allocation data or corrections received by Transporter after
it has closed the previous Month of flow shall be handled as a
prior period adjustment. Transporter shall process late
allocation data or corrections of allocation errors as soon as
practicable but no later than six Months after the applicable
Month of flow in question with a three Month rebuttal period.
These deadlines do not apply in the case of deliberate omission or
misrepresentation by a party (or its representative) or mutual
mistake of fact. The parties' other statutory or contractual
rights shall not be diminished by this provision. The correction
shall be made to the Month of flow with a restated line item and a
new total quantity of gas for the specific Day(s) and the
respective Month.