Nautilus Pipeline Company, LLC
Original Volume No. 1
Contents / Previous / Next / Main Tariff Index
Effective Date: 12/01/1997, Docket: CP96-790-003, Status: Effective
Original Sheet No. 114 Original Sheet No. 114 : Effective
GENERAL TERMS AND CONDITIONS
10. SERVICE REQUESTS AND CONTRACTING FOR SERVICE con't
firm capacity to Shippers having an unsatisfied
pre-November 1, 1996, Request for firm service
under Rate Schedule FT-1, Rate Schedule FT-2, and
Rate Schedule FT-3 in the order of the highest
economic value to Transporter on a net present
value basis, using as a discount factor the
Federal Reserve Board's Federal Funds Rate. All
capacity related to unsatisfied pre-November 1,
1996, Requests for service having the same
economic value to Transporter shall be allocated
among Shippers on a pro rata basis.
(b) The transportation service Request Date for all
Requests for firm transportation service under
Rate Schedule FT-1, Rate Schedule FT-2, or Rate
Schedule FT-3 received after 4:00 p.m. Houston,
Texas, time on October 31, 1996, shall be the
date Transporter receives a valid request
pursuant to this Section 10. All such requests
received on the same Day shall be deemed to have
the same date, and if the sum of all Requests for
firm service under Rate Schedule FT-1, Rate
Schedule FT-2, and Rate Schedule FT-3 exceeds the
certificated capacity of Transporter's Pipeline
Facilities then the available firm capacity shall
be allocated in the order of the highest economic
value of the bids to Transporter on a net present
value basis, using as a discount factor the
Federal Reserve Board's Federal Funds Rate. All
capacity related to Requests for firm service
under Rate Schedule FT-1, Rate Schedule FT-2, and
Rate Schedule FT-3 having the same economic value
to Transporter shall be allocated among Shippers
on a pro rata basis.