Nautilus Pipeline Company, LLC
Original Volume No. 1
Contents / Previous / Next / Main Tariff Index
Effective Date: 04/05/2010, Docket: RP10-475-000, Status: Effective
First Revised Sheet No. 47 First Revised Sheet No. 47
Superseding: Original Sheet No. 47
RATE SCHEDULE FT-3
FIRM TRANSPORTATION SERVICE
4. APPLICABILITY AND CHARACTER OF SERVICE con't
4.2 Transporter shall have no obligation to accept any Natural Gas for
transportation under this Rate Schedule FT-3 other than Natural Gas
produced from the OCS Field(s) and Leasehold Interest(s) identified on
Exhibit "A" to Shipper's FT-3 Service Agreement.
4.3 Transporter shall have no obligation to add any facilities or
expand the capacity of its Pipeline facilities beyond the initial
certificated capacity in any manner in order to provide transportation
service under this Rate Schedule.
4.4 Nominations and scheduling of service under this Rate Schedule
shall be in accordance with the procedures set out in Sections 11 and 12
of the GT&C of Transporter's Tariff.
4.5 Allocations of capacity shall be determined in accordance with
Section 10 of the GT&C of Transporter's Tariff.
5. THROUGHPUT COMMITMENT
5.1 Shipper shall ship through Transporter's Pipeline Facilities under
this Rate Schedule each Contract Quarter its "Throughput Commitment"
which shall equal at least eighty-five percent (85%) of Shipper's
contract entitlement for the relevant Contract Quarter. Shipper's
contract entitlement for any given Contract Quarter shall be equal to
the sum of the product of the MDTQ set forth on Exhibit "B" to its
Service Agreement for such Contract Quarter multiplied by the number of
Days in such Contract Quarter. Failure to satisfy the Throughput
Commitment shall subject Shipper to the payment of the conditional
reservation charge under Section 8.2(e) of this Rate Schedule.