Nautilus Pipeline Company, LLC
Original Volume No. 1
Contents / Previous / Next / Main Tariff Index
Effective Date: 04/05/2010, Docket: RP10-475-000, Status: Effective
First Revised Sheet No. 32 First Revised Sheet No. 32
Superseding: Original Sheet No. 32
RATE SCHEDULE FT-2
FIRM TRANSPORTATION SERVICE
11. REDUCTIONS IN CAPACITY con't
(b) Transporter shall grant the requested reduction if
Transporter agrees that it is adequately supported by Shipper's
data. However, if Shipper and Transporter fail to agree on a new
production profile within thirty (30) Days following Shipper's
requested reduction, Shipper shall submit Shipper's proposed
production profile and supporting data to one of the engineering
firms listed on Appendix "A" to Rate Schedule FT-2. The
engineering firm shall prepare a report, including a production
profile based on its analysis of the supporting data and
reflecting the impact of the requested reduction on future period
MDTQs, which shall be binding on Shipper and Transporter for
purposes of establishing Shipper's requested MDTQs under this Rate
Schedule. All costs and fees due to the engineering firm with
respect to the development of the production profile and MDTQs
shall be shared equally between Shipper and Transporter.
(c) If Shipper believes that the MDTQs contained in the
engineering report are inadequate to permit delivery of all of
Shipper's Natural Gas production from the OCS Field(s) and
Leasehold Interest(s) committed to this Rate Schedule under