Nautilus Pipeline Company, LLC
Original Volume No. 1
Contents / Previous / Next / Main Tariff Index
Effective Date: 12/01/1997, Docket: RP97-446-001, Status: Effective
First Revised Sheet No. 30 First Revised Sheet No. 30 : Effective
Superseding: Original Sheet No. 30
RATE SCHEDULE FT-2
FIRM TRANSPORTATION SERVICE
8. RATES AND CHARGES con't
(d) An Authorized Overrun charge for each MMBtu of
Natural Gas shipped pursuant to Section 7 of this
Rate Schedule equal to the maximum rate for such
service under this Rate Schedule as set forth on
the currently effective Sheet No. 9 of
Transporter's Tariff or such discounted rate
offered to Shipper by Transporter pursuant to
Section 27.1 of the GT&C of Transporter's Tariff;
(e) For any Contract Year in which Shipper (1) does
not satisfy the Throughput Commitment of Section
5.1 of this Rate Schedule, and (2) does not elect
to reduce its capacity entitlement pursuant to
Section 11.2 of this Rate Schedule a conditional
reservation charge equal to the Daily Conditional
Reservation rate stated on the currently
effective Sheet No. 9 of Transporter's Tariff or
such lesser rate charged to Shipper under Section
8.2(a), above, multiplied by a quantity of
Natural Gas equal to the difference between the
quantity of Natural Gas that would have been
shipped by Shipper under its Rate Schedule FT-2
Service Agreement had Shipper shipped one hundred
percent (100%) of its MDTQ each Day of such
Contract Year and the actual quantity of Natural
Gas shipped by Shipper under its Rate Schedule
FT-2 Service Agreement in such Contract Year as
determined by Section 5.2 of this Rate Schedule;
(f) For each Dth of capacity released by Shipper to a
Replacement Shipper under Section 14 of this Rate
Schedule an amount equal to the Conditional
Reservation charge for service under this Rate
Schedule as set forth on the currently effective
Sheet No. 9 of Transporter's Tariff less any
amounts credited to Shipper pursuant to Section
22.5 of GT&C; and