Nautilus Pipeline Company, LLC
Original Volume No. 1
Contents / Previous / Next / Main Tariff Index
Effective Date: 04/05/2010, Docket: RP10-475-000, Status: Effective
First Revised Sheet No. 26 First Revised Sheet No. 26
Superseding: Original Sheet No. 26
RATE SCHEDULE FT-2
FIRM TRANSPORTATION SERVICE
5. THROUGHPUT COMMITMENT con't
FT-2 Service Agreement Shipper's Throughput Commitment shall be equal to
eighty-five percent (85%) of the sum of the product of the MDTQs for the
third and fourth Contract Quarters multiplied by the number of Days in
each respective Contract Quarter. Failure to satisfy the Throughput
Commitment may subject Shipper to the payment of the conditional
reservation charge or a reduction of capacity under Sections 8.2(e) and
11.2, respectively, of this Rate Schedule.
5.2 For purposes of determining whether Shipper has satisfied its
Throughput Commitment under Section 5.1, above, Shipper's throughput for
the Contract Year shall include (a) any quantity of Natural Gas which
Shipper tenders for delivery and which is transported by Transporter
under this Rate Schedule FT-2 up to Shipper's MDTQ; (b) any quantity of
Natural Gas which Shipper nominates and tenders for delivery under its
Rate Schedule FT-2 Service Agreement at the Point(s) of Receipt but
which is not transported by Transporter unless Transporter's failure to
transport is the result of (i) the failure of Shipper's Natural Gas to
meet the quality specifications of Section 3 of the GT&C of
Transporter's Tariff, (ii) Transporter's determination that delivery of
Shipper's nominated quantities cannot be made at the designated Point(s)
of Delivery, or (iii) Transporter's determination that Shipper's title
or right to deliver Natural Gas to Transporter is questioned or involved
in any action; (c) all quantities of Natural Gas shipped by Shipper as
Authorized Overrun under Section 7 of this Rate Schedule; and (d) all
quantities of capacity released by Shipper under Section 14 of this Rate
Schedule.