4. APPLICABILITY AND CHARACTER OF SERVICE con't
4.2 Transporter shall have no obligation to accept any Natural Gas for
transportation under this Rate Schedule FT-2 other than Natural Gas
produced from the OCS Field(s) and Leasehold Interest(s) identified on
Exhibit "A" to Shipper's FT-2 Service Agreement.
4.3 Transporter shall have no obligation to add any facilities or
expand the capacity of its Pipeline facilities beyond the initial
certificated capacity in any manner in order to provide transportation
service under this Rate Schedule.
4.4 Nominations and scheduling of service under this Rate Schedule
shall be in accordance with the procedures set out in Sections 11 and 12
of the GT&C of Transporter's Tariff.
4.5 Allocations of capacity shall be determined in accordance with
Section 10 of the GT&C of Transporter's Tariff.
5. THROUGHPUT COMMITMENT
5.1 Shipper shall ship through Transporter's Pipeline Facilities under
this Rate Schedule each Contract Year its "Throughput Commitment" which
shall equal at least eighty-five percent (85%) of Shipper's contract
entitlement for the relevant Contract Year. Shipper's contract
entitlement for any given Contract Year shall be equal to the sum of the
products of the MDTQ set forth on Exhibit "B" to its Service Agreement
for each of the four (4) Contract Quarters of the relevant Contract Year
multiplied by the number of Days in each such Contract Quarter.
Provided, however, for the first Contract Year of service under its Rate
Schedule