20. REQUESTS FOR ADDITIONAL FACILITIES/EXPANDED CAPACITY

 

20.1 Shipper may request, by use of the Service Request Form, the

addition of facilities or expansion of Transporter's Facility to

allow the requesting Shipper to deliver/receive specified gas

quantities under an existing or new Transportation Service

Agreement.

 

20.2 Transporter shall determine the following information in response

to the above request:

 

(a) the estimated cost of constructing and installing the

requested additional facilities or modifying existing

facilities (new facilities costs) and an estimated time to

accomplish such.

 

(b) assess the impact of the requested additional facilities or

modified existing facilities on Transporter's ability to

operate its system and continue to provide service pursuant

to then existing Transportation Service Agreements.

 

20.3 Transporter shall transmit the above information in writing to the

requesting Shipper.

 

20.4 If Transporter's assessment of the impact to its system is not

negative, then based on the new facilities cost, if the requesting

Shipper continues to desire to have the additional facilities

added to Transporter's system or existing facilities modified, the

requesting Shipper and Transporter shall then execute the

documents required to implement the requested service - new or

amended Transportation Service Agreement, amended Exhibit "A",

etc., conditioned upon reaching agreement on terms and conditions

satisfactory to each Transporter and Shipper in their individual

sole judgment.