Garden Banks Gas Pipeline, LLC
Original Volume No. 1
Contents / Previous / Next / Main Tariff Index
Effective Date: 09/01/2005, Docket: RP05-453-000, Status: Effective
First Revised Sheet No. 85A First Revised Sheet No. 85A : Effective
Superseding: Original Sheet No.85A
GENERAL TERMS AND CONDITIONS
(f) The predetermined allocation statement for
Receipt Points interconnecting with third-
party pipelines shall be provided by the
third-party pipeline and shall rank the
various Transportation Service Agreements to
be supplied at the Receipt Point in
accordance with one of the methodologies
enumerated in subsection 12.1(b)(ii). In
the event there is a conflict between the
foregoing methodologies and the third-party
pipeline's provision in its FERC Gas Tariff
governing the allocations of deliveries,
said pipeline company and Transporter shall
mutually agree on the predetermined
allocation methodology to be used. The
ranking shall include the contract number
assigned by Transporter to each
Transportation Service Agreement and the
name of the Shipper thereunder.