Garden Banks Gas Pipeline, LLC
Original Volume No. 1
Contents / Previous / Next / Main Tariff Index
Effective Date: 05/10/2010, Docket: RP10-594-000, Status: Effective
Second Revised Sheet No. 79C Second Revised Sheet No. 79C
Superseding: First Revised Sheet No. 79C
11.1 Nomination Procedures (cont'd)
Scheduled quantities resulting from Intraday 1
Nominations should be effective at 5:00 p.m. CCT on
gas day.
(iv) The Intraday 2 Nomination Cycle:
The nomination time line on the day of gas flow
shall be the following:
5:00 p.m. CCT Nomination leaves control of
nominating party
5:15 p.m. CCT Receipt of nomination by
Transporter (including from
TTTSPs)
5:30 p.m. CCT Send Quick Response
8:00 p.m. CCT Receipt of completed
confirmations by Transporter from
upstream and downstream connected
parties
9:00 p.m. CCT Transporter provides scheduled
quantities to affected shippers
and point operators.
Scheduled quantities resulting from Intraday 2
Nominations should be effective at 9:00 p.m. CCT
on gas day. Bumping is not allowed during the
Intraday 2 Nomination Cycle.
(v) For purposes of 11.1 (b) (ii), (iii), and (iv)
above, "provide" shall mean, for transmittals
pursuant to standards 1.4.x, receipt at the
designated site, and for purposes of other forms
of transmittal, it shall mean send or post.
(vi) Model: Refer to Standard 1.3.2, version 1.3
(c) Intraday nominations are for one day only. Intraday
nominations may be used to nominate new supply or
market.