GENERAL TERMS AND CONDITIONS
6. PRESSURE
6.1 Receipt Point(s):
All gas to be transported for Shipper shall be delivered to
Transporter at pressures sufficient to enter Transporter's
Facility at such working pressures maintained by Transporter at
each Receipt Point; provided, however, that such pressures
shall not exceed Transporter's maximum allowable operating
pressures at each such point. Transporter shall operate its
system so that the pressure at each Receipt Point shall not
exceed the lesser of the Maximum Receipt Point Pressure as
stated on Exhibit "A" of the applicable Transportation Service
Agreement(s) or 1750 psig.
6.2 Delivery Point(s):
Gas will be delivered by Transporter at each Delivery Point on
Exhibit "A" to the Transportation Service Agreement at the
working pressures maintained by Transporter from time to time,
but not greater than the Maximum Delivery Point Pressure as
stated on Exhibit "A" to the applicable Transportation Service
Agreement(s).