Garden Banks Gas Pipeline, LLC
Original Volume No. 1
Contents / Previous / Next / Main Tariff Index
Effective Date: 05/10/2010, Docket: RP10-594-000, Status: Effective
First Revised Sheet No. 11 First Revised Sheet No. 11
Superseding: Original Sheet No. 11
RATE SCHEDULE FT-1
FIRM TRANSPORTATION SERVICE
or for Shipper's account up to the Maximum Daily Delivery Quantity
at the Delivery Point(s) specified in Exhibit "A" to the executed
FT-1 Transportation Service Agreement, all on a firm basis.
Transporter shall not commence service until Transporter and
Shipper have executed an FT-1 Transportation Service Agreement.
2.3 Transporter shall not be required to install, operate or maintain
any additional facilities in order to provide transportation
service under this Rate Schedule. A New Facilities Charge shall
not apply to any of Transporter's Facility constructed pursuant to
the certificate issued in Docket No. CP96-307-000 or Docket No.
CP96-307-002.
2.4 Service under this Rate Schedule shall be nominated in accordance
with the procedures set forth in Section 11 of Transporter's
General Terms and Conditions.
2.5 Capacity available for firm transportation shall be allocated
among Shippers receiving service under Rate Schedules FT-1 and FT-
2 in accordance with Section 11 of the General Terms and
Conditions of Transporter's FERC Gas Tariff.
3. DELIVERY AND RECEIPT POINTS, PRESSURES, UNIFORM QUANTITIES
3.1 Receipt Points: The Primary Receipt Point(s) on Transporter's
Facility shall be specified on Exhibit "A" to the FT-1
Transportation Service Agreement.
3.2 Delivery Points: The Primary Delivery Point(s) on Transporter's
Facility shall be specified on Exhibit "A" to the FT-1
Transportation Service Agreement. Transporter shall not be
obligated to accept gas hereunder for transportation to any
Delivery Point(s) at which the downstream pipeline has
insufficient capacity, or is unable, to accept the gas for
delivery.
3.3 Pressures: Shipper shall deliver gas to Transporter at the
pressure required from time to time to enable the gas to enter
Transporter's Facility at the Receipt Point(s). Transporter shall
operate Transporter's Facility at a maximum pressure at the
Receipt Points of 1750 psig. In no event shall Transporter be
required to install compression to effect deliveries hereunder.