Garden Banks Gas Pipeline, LLC

Original Volume No. 1

 Contents / Previous / Next / Main Tariff Index

 

 

Effective Date: 05/10/2010, Docket: RP10-594-000, Status: Effective

First Revised Sheet No. 11 First Revised Sheet No. 11

Superseding: Original Sheet No. 11

 

RATE SCHEDULE FT-1

FIRM TRANSPORTATION SERVICE

 

 

or for Shipper's account up to the Maximum Daily Delivery Quantity

at the Delivery Point(s) specified in Exhibit "A" to the executed

FT-1 Transportation Service Agreement, all on a firm basis.

Transporter shall not commence service until Transporter and

Shipper have executed an FT-1 Transportation Service Agreement.

 

2.3 Transporter shall not be required to install, operate or maintain

any additional facilities in order to provide transportation

service under this Rate Schedule. A New Facilities Charge shall

not apply to any of Transporter's Facility constructed pursuant to

the certificate issued in Docket No. CP96-307-000 or Docket No.

CP96-307-002.

 

2.4 Service under this Rate Schedule shall be nominated in accordance

with the procedures set forth in Section 11 of Transporter's

General Terms and Conditions.

 

2.5 Capacity available for firm transportation shall be allocated

among Shippers receiving service under Rate Schedules FT-1 and FT-

2 in accordance with Section 11 of the General Terms and

Conditions of Transporter's FERC Gas Tariff.

 

3. DELIVERY AND RECEIPT POINTS, PRESSURES, UNIFORM QUANTITIES

 

3.1 Receipt Points: The Primary Receipt Point(s) on Transporter's

Facility shall be specified on Exhibit "A" to the FT-1

Transportation Service Agreement.

 

3.2 Delivery Points: The Primary Delivery Point(s) on Transporter's

Facility shall be specified on Exhibit "A" to the FT-1

Transportation Service Agreement. Transporter shall not be

obligated to accept gas hereunder for transportation to any

Delivery Point(s) at which the downstream pipeline has

insufficient capacity, or is unable, to accept the gas for

delivery.

 

3.3 Pressures: Shipper shall deliver gas to Transporter at the

pressure required from time to time to enable the gas to enter

Transporter's Facility at the Receipt Point(s). Transporter shall

operate Transporter's Facility at a maximum pressure at the

Receipt Points of 1750 psig. In no event shall Transporter be

required to install compression to effect deliveries hereunder.