14.2 Application of Payments for Released Capacity. Payments to Egan Hub by a
Replacement Customer for released capacity shall be applied as follows: (i) Egan Hub shall
retain amounts equal to the Replacement Customer's usage charges; (ii) Egan Hub will credit the
balance to Reservation Charges due from the Replacement Customer; and (iii) Egan Hub shall
remit the remaining balance, if any, or shall charge any balance due, to the Replacement
Customer, in accordance with Section 4.10 of the General Terms and Conditions of this FERC Gas
Tariff. If any balance due from the Replacement Customer remains unpaid, the outstanding
balance will then be billed to the Releasing Customer, provided that the Releasing Customer is
only liable to the extent of its Reservation Charges.
14.3 Payment. Customer shall pay Egan Hub by wire transfer the full amount reflected
on the invoice within ten (10) days of the date of the invoice. If the tenth (10th) day shall
fall upon a weekend or legal holiday, then such payment shall be made on the last regular
Business Day prior to such tenth (10th) day. Party making payment should submit supporting
documentation; party receiving payment should apply payment per supporting documentation
provided by the paying party; and if payment differs from invoiced amount, remittance detail
should be provided with the payment except when payment is made by electronic funds transfer
(EFT), in which case, the remittance detail is due within two Business Days of the payment due
date.
14.4 Billing Error. If an error is discovered in any billing, such error shall be
adjusted within thirty (30) days of the determination thereof.
14.5 Billing Disputes. If a dispute arises as to the amount payable in any invoice
rendered hereunder, Customer shall nevertheless pay when due the amount not in dispute under
such invoice and shall submit to Egan Hub a written explanation of the dispute and any
available supporting document. Such documentation shall be provided to Egan Hub at the time
that the payment is due. Such payment shall not be deemed to be a waiver of the right by
Customer to recoup any overpayment, nor shall acceptance of any payment be deemed to be a
waiver of the right by Customer to recoup any overpayment, nor shall acceptance of any payment
be deemed to be a waiver by Egan Hub of any underpayment. The parties shall then cooperate in
good faith to resolve such dispute as expeditiously as possible, and the portion, if any, of
such disputed amount eventually determined to be due shall bear interest at the rate stated in
Section 14.4 above from the original due date until the date actually paid. In the event
Customer fails to forward the entire undisputed amount due to Egan Hub when same is due,
interest on the unpaid portion shall accrue at the same rate of interest and in the same manner
as prescribed for pipeline refunds as set forth in Section 154.501(d) of the Commission's
regulations under the Natural Gas Act from the date such payment is due until the same is paid.
If Customer's failure to pay the undisputed portion of any invoice rendered hereunder continues
beyond thirty (30) days after the due date of such invoice, then Egan Hub, in addition to all
other legal remedies available to it, shall have the right and option to suspend further
deliveries of Gas until such default shall have been cured. If Customer's failure to pay the
undisputed portion of any invoice rendered hereunder continues beyond sixty (60) days after the
due date of such invoice, then Egan Hub, in addition to all other legal remedies available to