Egan Hub Storage, LLC
First Revised Volume No. 1
Contents / Previous / Next / Main Tariff Index
Effective Date: 02/01/2009, Docket: RP09-160-000, Status: Effective
Fourth Revised Sheet No. 135 Fourth Revised Sheet No. 135
Superseding: Third Revised Sheet No. 135
GENERAL TERMS AND CONDITIONS
(Continued)
12:00 p.m. Egan Hub provides quick response for validity of data
elements
3:30 p.m. Completed confirmations from upstream and downstream
connected parties provided to Egan Hub
4:30 p.m. Receipt of scheduled quantities by Customer and point
operator
The sending party shall adhere to nomination, confirmation, and scheduling deadlines. It
is the party receiving the request who has the right to waive the deadline.
(b) Intra-day Nominations. Any nomination received during a Gas Day for the same Gas
Day, or any nomination received after the nominations deadline set forth in Section 8.2(a)
above for the following Gas Day shall be an Intra-day Nomination. Intra-day Nominations can be
used to request increases or decreases in total flow, changes to receipt points, or changes to
delivery points of scheduled Gas. Intra-day Nominations do not rollover (i.e. Intra-day
Nominations span one Day only). Intra-day Nominations do not replace the remainder of a
standing nomination. There is no need to re-nominate if Intra-day Nomination modifies existing
nomination. Intra-day Nominations may be used to nominate new injections or withdrawals. All
nominations, including Intra-day Nominations, shall be based on a daily quantity; thus, an
intra-day nominator need not submit an hourly nomination. Intra-day Nominations shall include
an effective date and time. The interconnected parties shall agree on the hourly flows of the
Intra-day Nomination, if not otherwise addressed in the interconnected parties' contract or
tariff.
In the event Customer does not submit a timely nomination or desires to alter an
existing nomination, Customer shall have the right to submit an Intra-day Nomination to revise
Customer's scheduled quantities, Point(s) of Receipt and/or Point(s) of Delivery on a
prospective basis prior to the end of the Gas Day; provided, however, that such Intra-day
Nomination will be processed after all timely nominations have been scheduled. Such Intra-day
Nomination shall be implemented by Egan Hub to the extent and only to the extent that Egan Hub
is able to confirm the receipt and delivery of such Gas at the Point(s) of Receipt and Point(s)
of Delivery.
(c) Elapsed-Prorated-Scheduled Quantity. With respect to Intra-day Nominations for
reductions in previously scheduled quantities, Egan Hub may accept any explicitly confirmed
quantity, down to and including zero, for such Intra-day Nomination; provided, however, if such
Intra-day Nomination requires confirmation from an upstream and/or downstream interconnected
pipeline, then any Intra-day Nomination to reduce previously scheduled quantities will be
subject to, and limited to, the reduced quantity confirmed by such upstream and/or downstream
interconnected pipeline.
(d) Nominations will be processed for scheduling in order by priority level as
described in Section 5 of the General Terms and Conditions of this FERC Gas Tariff.
Nominations received after nomination deadline shall be scheduled after the nominations
received before the nomination deadline.
(e) Notices provided under this Section 8.2 must be submitted via the LINK® System,
unless another method of submittal is mutually agreed upon by Customer and Egan Hub. Customer
shall provide notice of any changes in deliveries to or receipt from Egan Hub to Customer's
Transporter(s) and shall be responsible for, and shall hold Egan Hub harmless from, any and all
liabilities and expense resulting from any such changes, unless the added expense is due to the
negligence of Egan Hub.