Egan Hub Storage, LLC
First Revised Volume No. 1
Contents / Previous / Next / Main Tariff Index
Effective Date: 02/01/2009, Docket: RP09-160-000, Status: Effective
Fourth Revised Sheet No. 83 Fourth Revised Sheet No. 83
Superseding: Third Revised Sheet No. 83
IBS RATE SCHEDULE
INTERRUPTIBLE BALANCING SERVICE
(Continued)
6. AUTHORIZATION, RATES, TERMS AND CHANGES
6.1 Customer's Hub Services Agreement and the respective obligations of the parties
hereunder are subject to all valid laws, orders, rules and regulations of duly constituted
authorities having jurisdiction, and are conditioned upon the issuance, by the FERC, and any
state or local governmental agency having jurisdiction, of requisite authorization for Egan Hub
to construct and operate the facilities necessary to provide the Interruptible balancing
service contemplated herein, and for any interconnected pipeline to transport Gas to/from the
Point(s) of Receipt/Delivery to effect the Interruptible balancing service provided for herein.
6.2 Egan Hub shall have the right to propose to the FERC or other governing regulatory
body such changes in its rates and terms of service as it deems necessary, and Customer's Hub
Services Agreement shall be deemed to include any changes which are made effective pursuant to
order or regulation or provisions of law, without prejudice to Customer's right to protest the
same; provided, however, that any negotiated rates between Egan Hub and its Customer(s) shall
remain in effect during the term of Exhibit B of Customer's Hub Services Agreement(s).
7. CURTAILMENT
If, due to any cause whatsoever, Egan Hub's capability to receive, store or deliver
quantities is impaired so that Egan Hub is unable to receive, store or deliver on any Gas Day
the quantities provided for in Exhibit B of the Hub Services Agreement with Customers, then
interruptible balancing capacity, withdrawals, and/or injections will be allocated according to
the priority of service as set forth in Section 5 of the General Terms and Conditions of this
FERC Gas Tariff.
8. EXPIRATION OF TERM
Prior to the end of the term of the applicable Exhibit B of Customer's Hub Services
Agreement, Customer must either physically withdraw the Gas or indicate to Egan Hub in writing
that it desires to have Egan Hub cash out the Gas on mutually agreeable terms. If, by the end
of the Gas Day that is the last Gas Day of the term of Exhibit B of Customer's Hub Services
Agreement, Customer neither has withdrawn the Gas nor indicated in writing to Egan Hub that it
desires to exercise the cash out option, then Egan Hub may take, free and clear of any adverse
claims, title to such IBS balance quantity as Customer was required, but failed, to withdraw or
cash out; provided, however, that only those quantities not withdrawn or cashed out on mutually
agreeable terms shall become the property of Egan Hub, free and clear of any adverse claims.