GENERAL TERMS AND CONDITIONS (Cont’d)
6.3 Confirmation and Scheduling by Seller.
(a) No gas shall flow under any nomination until Seller has confirmed
the nomination, awarded capacity, and scheduled the applicable quantities.
If Customer’s gas is not confirmed on the same day in which capacity is
nominated, the nomination of that Customer shall be void and the capacity
shall be offered to the next eligible Customer.
(b) Seller shall initiate confirmation (Request for Confirmation) with
the Confirming Party or respond to request for confirmation (Confirmation
Response) from the Confirming Party. Seller shall complete confirmations by
the following deadlines:
(1) The Timely Nomination Cycle: Confirmation shall be completed by
3:30 pm (C.T.) the day before the start of the Gas Day.
(2) The Evening Nomination Cycle: Confirmation shall be completed by
9:00 pm (C.T.) the day before the start of the Gas Day.
(3) The Intraday 1 Nomination Cycle: Confirmation shall be completed
by 1:00 pm (C.T.) on the Gas Day.
(4) The Intraday 2 Nomination Cycle: Confirmation shall be completed
by 8:00 pm (C.T.) on the Gas Day.
(c) Seller shall provide to Customers and Point Operator their
scheduled quantities by the following timelines and provisions:
(1) The Timely Nomination Cycle: Scheduled Quantities shall be
provided by 4:30 pm (C.T.) the day before the start of the Gas Day.
(2) The Evening Nomination Cycle: Scheduled Quantities shall be
provided by 10:00 pm (C.T.) the day before the start of the Gas Day.
(3) The Intraday 1 Nomination Cycle: Scheduled Quantities shall be
provided by 2:00 pm (C.T.) on the Gas Day.