Northern Border Pipeline Company
First Revised Volume No. 1
Contents / Previous / Next / Main Tariff Index
Effective Date: 02/01/2009, Docket: RP09-132-000, Status: Effective
Fourth Revised Sheet No. 112 Fourth Revised Sheet No. 112
Superseding: Third Revised Sheet No. 112
RATE SCHEDULE FCS-DP
FIRM COMPRESSION SERVICE - DES PLAINES
3. RATES (Continued)
3.5 Remedies for Failure to Pay Bills
Subject to the notice terms of Subsection 6.3(b) of the
General Terms and Conditions, Company may, after it files
and receives any necessary regulatory authorization,
terminate Shipper's Service Agreement under this Rate
Schedule.
4. COMPRESSOR FUEL GAS
Shipper shall furnish the Compressor Fuel Gas Percentage, as
specified in the Statement of Rates for this Rate Schedule, which
shall be applied to Shipper's total scheduled quantity at the
receipt point under this Rate Schedule on any given Gas Day.
The term "Compressor Fuel Gas" for any period shall mean the total
quantity of gas, including but not limited to gas used as fuel or
for testing and gas lost or otherwise unaccounted for, used by
Company in its gas operations of the Des Plaines Compressor
Station during such period, as determined by Company.
The term "Compressor Fuel Gas Percentage" is the fuel percentage
applied to the scheduled receipt nominations received at
DP Receipt Point for the Compressor Fuel Gas.
5. TERMINATION
If a Service Agreement under this Rate Schedule is not continued
in accordance with Section 6 of Rate Schedule T-1, such Service
Agreement shall terminate under the terms of the Rate
Schedule FCS-DP Service Agreement.
6. INCORPORATION BY REFERENCE
Section 5 of Rate Schedule T-1 is incorporated by reference. For
the purposes of this Rate Schedule only, the references in
Section 5 to "Rate Schedule T-1" or "Service Agreement" and "U.S.
Shipper Service Agreement" shall be interpreted as "Rate
Schedule FCS-DP" and "Rate Schedule FCS-DP Service Agreement".