Triennial Reviews
Southwest Power Pool Region (SPP)
The Commission will review each region every three years according to a rotating schedule. The SPP region will be reviewed on the following dates, and every three years thereafter, depending on what type of entity the seller is.

| SPP Schedule for Filing from Order 697-A |
| Study Period |
Filing Period |
Entities Required to File |
| December 1, 2009 - November 30, 2010 |
June, 2012 |
SPP Transmission Owners |
| December 1, 2009 - November 30, 2010 |
December, 2012 |
Others in SPP that did not file in June and have not been found to be Category 1 sellers. |
| December 1, 2012 - November 30, 2013 |
June, 2015 |
SPP Transmission Owners |
| December 1, 2012 - November 30, 2013 |
December, 2015 |
Others in SPP that did not file in June and have not been found to be Category 1 sellers. |
|
|